DIRECTORY  HOME   

 

  
City of Rahway
1 City Hall Plaza
Rahway, NJ 07065
(732) 827-2000
 

 

 


 

October 29, 2003

COMBINED SEWER OVERFLOW (CSO) SEPARATION PROJECT UPDATE

The city’s Combined Sewer Overflow (CSO) project is a five-year project to upgrade Rahway’s storm and sanitary sewer systems.  The project commenced in February 2000 and will be complete by December 2004.  The project is required as part of an Administrative Consent Order reached with the city and the New Jersey Department of Environmental Protection.

Many older areas of Rahway were constructed with a combined sewer that carries both sanitary waste from homes and businesses as well as stormwater runoff from streets and properties.  Both the sanitary waste and stormwater travel through this combined system to the Rahway Valley Sewerage Authority plant for treatment.  During heavy rainstorms, the system is unable to handle the increased flow of water and waste and may be discharged into the Rahway River and its tributaries.  In addition to the health hazards this may cause, city taxpayers were unnecessarily paying for the treatment of stormwater at the RVSA facility.

The combined sewer overflow and sewer separation project consists of disconnecting the roadway storm sewer catch basins and pipes from the remaining combined storm and sanitary sewer system.  Once this work is complete the potential for sanitary sewer overflow into the local rivers will be eliminated, and therefore maintain and improve the water quality of the rivers flowing from the city.

The construction portion of this project is divided into two phases, Phases I and II.  Phase I construction is complete and was done by Niram, Inc. of Boonton, New Jersey.  Phase II construction is approximately 50 percent complete and is being done by JFS Development and Associates, LLC of Hackensack, New Jersey.  The storm sewer separation work that is underway this fall is or is being conducted along the following streets: Bryant Street, West Milton Avenue, West Cherry Street, Monroe Street, Main Street and East Cherry Street.

During 2004, the final phase of the project will consist of testing and the closure of the combined sewer overflow outlets to the rivers.

The cost of the project, approximately $3,375,000.00, is funded through the New Jersey Environmental Infrastructure Financing Program.

NEWS

October 3, 2008
Downtown Sewer Flooding to be resolved through citywide effort. more,

October 1, 2008
Leaf collection begins November 5. more,

September 18, 2008
FEMA’S national flood hazard map available via Google Earth. more,

September 15, 2008
Clerk's office to be open late for voter registration Oct. 14. more,

March 19, 2008
Traffic direction to change downtown. more,

January 7, 2008
Mayor Kennedy's 2008 State of the City Address. more,

Press Release Archive